試題題型【單選題】
試題內容

Project schedule management is made up of six management processes including:activity definition, activity sequencing,(  ) , and schedule control by order.
A.activity duration estimating, schedule developing, activity resource estimating
B .activity resource estimating, activity duration estimating, schedule development
C.schedule developing, activity resource estimating, activity duration estimating
D.activity resource estimating, schedule developing, activity duration estimating