試卷名稱 2017年信息系統(tǒng)項目管理師最新英語模擬題(5)
考試中心《2017年信息系統(tǒng)項目管理師最新英語模擬題(5)》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

To meet the schedule,a decision was made to outsource part of a project to an external manufacture. What steps should a project manager follow to assess potential suppliers before awarding a contract?
A、Bidder conferences,independent estimate,and procurement negotiations
B、Quantitative analysis,bidder conferences,and critical path analysis
C、Procurement negotiations,independent estimate,and performance report
D、Procurement performance review,expert judgment and proposal evaluation technique